Pickersgill Construction was fully paid for cement work in my backyard. Not all of the work was completed and messages are no longer being returned.
On July 10, 2017 I received a quote from *** of Pickersgill Construction Ltd. There were three phases to the quote. Phase 1 included pouring a foundation and putting stone down and framing the portion of my backyard patio. The cost of phase 1 was $5,000 cash. *** asked to be paid in full after the foundation was poured which I agreed to.
*** started work on my property (***, Tecumseh) in late July and received his full payment for phase 1 on August 11. In addition, during this time, my driveway had piles of dirt and concrete deposited by *** that he said would be removed after completion
of phase 1. He did not remove the dirt and concrete and I had to pay another contractor $300 to remove it.
I began following up via text messages (copies retained) and phone calls a week later.
Text messages were sent on the following dates:
August 18- Response by *** was he would be here ASAP
August 24 - No response from ***
August 28 - No response from ***
August 31 - No response from ***, I mentioned phase 1 was not finished and wanted him to confirm laying the stone and framing was part of phase 1
September 3 - Response from *** on September 5 that he was away for the long weekend and got the flu; was trying to come by on the 6th to get things back on track
September 6 - Response from *** was that he would arrive before 12:30 on September 7
September 12 and 13 - Response from *** was that he would be there on September 15
September 18 - No response from ***
September 19 - No response from ***, I commented that phase 1 was still not complete
September 20- Response from *** was he would be there on the September 21, the 22nd at the latest
September 22 - No response from ***
September 25 - No response from ***
September 26 - No response from ***
September 28 - No response from ***, I commented phase 1 was fully paid but not complete
October 2 - Informed *** I have reached out to another contractor to finish phase 1 and would be asking him to pay portion for stone and framing - No response from ***
November 13 - provided *** an estimate for work I paid for which he didn't complete and asked him to try and negotiate a settlement and if I did not hear back from him I would file a claim in small claims court
Phone calls were made from cell phone (519-819-1025) to ***'s cell phone (519-919-2418) on the following dates. Note: my cell phone does not have call details prior to September 25
September 25
September 26 - 3 calls
September 28 - message left
September 30
October 2 - 2 calls, 1 message left
November 17 - 2 calls, 1 message left
I would like to be reimbursed $1,500. $1,200 for the framing and laying stone that was part of phase 1. $300 is the cost for removal of dirt and cement left in my driveway. Both amounts above were provided by the contractor who completed the work.